W912HY26BA021ActiveCONTRACT

GIWW Freeport to Matagorda Maintenance Dredging

Department of DefenseW076 ENDIST GALVESTON

AI Overview

This amendment adjusts contract timelines for FY26 GIWW Freeport to Matagorda Bay maintenance dredging operations. Delivery schedules are reduced from 225 to 210 calendar days for primary work and extended from 35 to 40 days for optional tasks.

This summary is AI-generated from the official solicitation.

Key Details

Agency
Department of Defense
Funding Amount
—
Release Date
September 10, 2026
Due Date
October 13, 2026

Official Description

--- Attachment text --- [Solicitation_Amendment_W912HY26BA0210003_SF_30.pdf] 11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of ...

View on official source

Change History

Description ChangedOct 9, 2026 at 3:38 PM

Critical change · Deadline + Scope + Requirements + Attachment + Description

GIWW Freeport to Matagorda Maintenance Dredging

  • Bid due date moved from October 13, 2026 to October 19, 2026 (10:00 a.m. local time), giving offerors six more days to submit.
  • Schedule 1 delivery period changed from 225 to 210 calendar days from Notice to Proceed receipt (the earlier amendment had set it at 225 days). Option Line Item 0015 through 0017 durations went from 35 to 40 calendar days, which is a schedule-time change that affects bid pricing and planning.
  • Amendment 0003 applies the Schedule 1 and Option No. 1 duration revisions across the listed CLINs (0001 through 0014 and options 0015 to 0017), shortening the main work period while the option periods are lengthened.
  • Bid opening remains October 19, 2026. All other terms are stated as unchanged.

Why it matters: applicants need to re-check their dredging schedules, equipment mobilization plans, and pricing against the new 210-day main-work window and 40-day option windows before submitting by October 19.

Description ChangedOct 6, 2026 at 8:38 PM

Informational change · Description

GIWW Freeport to Matagorda Maintenance Dredging

  • Bid deadline moved: from October 13, 2026 at 10:00 a.m. local time to October 19, 2026 at 10:00 a.m. local time.
  • Bid Schedule quantities were updated. The amendment excerpt does not list the revised quantities; use the amended Bid Schedule when preparing pricing.
  • Schedule 1 delivery period is set at 225 calendar days. Applicants should account for this duration in their schedule and pricing.
  • Section 00 73 00 now includes a Variation in Estimated Quantity provision; required FAR clauses are incorporated, and FAR 52.232-15 is removed. Review the revised terms for effects on quantity and contract administration.
  • Section 35 20 23.16 45 and drawings CN301 through CN316 are replaced by amended versions. Base bids on those revised technical documents.
Description ChangedSep 25, 2026 at 7:46 PM

Informational change · Description

GIWW Freeport to Matagorda Maintenance Dredging

Description information changed.

Description ChangedSep 22, 2026 at 5:57 PM

Material change · Description + Attachment

GIWW Freeport to Matagorda Maintenance Dredging

Contact information was removed and replaced with a detailed technical PDF attachment containing project specifications and engineering documentation.

Opportunity AddedSep 21, 2026 at 11:22 PM

GIWW Freeport to Matagorda Maintenance Dredging

New opportunity: GIWW Freeport to Matagorda Maintenance Dredging

Similar Opportunities

Get Alerts for Opportunities Like This

RallyProp monitors thousands of funding sources and sends instant alerts when opportunities match your technology and capabilities.

Start Free Trial