RallyPropRallyProp.ai

This solicitation closed on November 6, 2026

View current Department of Defense opportunities →
W912HP27RA002ClosedRFI

Trade and Cargo Academy

Department of DefenseW074 ENDIST CHARLESTON

AI Overview

A construction solicitation amendment for a Trade and Cargo Academy facility at FLETC, covering site work, environmental testing requirements, deep foundation protections, and HVAC and demolition updates. It is a standard building project with no research or novel technology focus.

This summary is AI-generated from the official solicitation.

Key Details

Agency
Department of Defense
Funding Amount
—
Release Date
September 17, 2026
Due Date
November 6, 2026 (Closed)

Official Description

--- Attachment text --- [B_08_03___Solicitation_Amend_03_2026_10_14___W912HP27RA002___FLETC_Trade___Cargo.pdf] 11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items ...

View on official source

Change History

Date ChangedOct 24, 2026 at 3:49 PM

Critical change · Deadline

Trade and Cargo Academy

The open date moved from September 17, 2026 to October 14, 2026, a shift of 27 days later. Applicants gain 27 extra days before the opportunity opens, so the start of the application window is delayed. Businesses planning proposal preparation, teaming arrangements, or capture activities around the original September date should re-baseline their schedules to mid-October. Because the close date was not reported as changed, the apparent effect is a shorter overall window if the close date remains fixed, so applicants should verify the closing deadline in the current solicitation.

Date ChangedOct 24, 2026 at 3:49 PM

Critical change · Deadline

Trade and Cargo Academy

The application close date moved later, from October 13, 2026 to November 6, 2026. That is a shift of 24 days, giving applicants roughly three and a half extra weeks to prepare and submit. Teams planning proposal timelines, partner commitments, or internal review cycles should update their schedules accordingly, though the later deadline does not change any other eligibility or submission requirements.

Description ChangedOct 14, 2026 at 8:54 PM

Material change · Deadline + Attachment + Requirements + Submission + Description

Trade and Cargo Academy

  • Attachment 11 (Instructions and Basis for Award) was replaced: the earlier version (dated 06 Oct 2026, filed as B.08.02) was swapped for a revised dated 10.6.2026 (B.08.03), and Attachment 14 (Site Visit Sign In Sheets) was added.
  • Proposal acceptance period shortened: offers must now remain valid for 60 calendar days instead of 120.
  • Volume IV proposal deadline extended to November 6, 2026 at 12:00pm local time; ProjNet bidder inquiries stay open until October 16, 2026 at 12:00pm.
  • New environmental testing requirement (Section 31 62 13.20 / 31 00 00): test results for any imported or relocated fill and for any excavation area must be submitted 60 days before the work begins.
  • Cooper Marl protection limit: the Cooper Marl layer, starting near 45 feet, is a confining unit, so pre-augering is capped at 45 feet below ground surface. This affects foundation and pile cost and method planning.
  • Design updates for the CSSPTF and TCA projects: revised drawings (including ductwork pressure/seal class), Building 286 demolition changes for prefabricated stairs, and a new channel liner installation detail.

Why it matters: bidders need to re-price foundations and earthwork, plan earlier environmental sampling, and confirm that their offer validity and Volume IV timing still work.

Status ChangedOct 13, 2026 at 5:41 PM

Informational change · Status

Trade and Cargo Academy

The solicitation's status changed from open to closed. Applicants can no longer submit proposals through this opportunity, so any application still in preparation will not be accepted under this announcement. Teams that planned to submit should check whether a follow-on or reopened notice has been posted, monitor the agency's grants or contracts portal for amendments, and redirect effort toward any other open opportunities that match their capabilities.

Description ChangedOct 7, 2026 at 5:39 PM

Informational change · Description

Trade and Cargo Academy

  • The solicitation replaces the prior Instructions and Basis for Award attachment with a revised version dated October 6, 2026. Applicants should review it for current proposal-submission and evaluation requirements, including how affiliate and team-member past performance is treated.
  • Site Visit Sign In Sheets are added as Attachment 14. Applicants should review them for relevant site-visit information.
  • The amendment does not state a change to the facilities’ construction scope.
Description ChangedSep 22, 2026 at 5:58 PM

Informational change · Description

Trade and Cargo Academy

Description information changed.

Opportunity AddedSep 21, 2026 at 11:22 PM

Trade and Cargo Academy

New opportunity: Trade and Cargo Academy

Similar Opportunities

Get Alerts for Opportunities Like This

RallyProp monitors 17 funding and innovation sources and sends instant alerts when opportunities match your technology and capabilities.

Build Your Free Lane