This solicitation closed on October 26, 2026
View current Department of Defense opportunities →Hickman Borings Drilling and Testing
AI Overview
Seeks a contractor to perform river-based roto-sonic drilling, rock coring, and laboratory geotechnical testing near Hickman, KY, to recover intact cemented sand and gravel samples. Work supports Army Corps of Engineers foundation design for a Mississippi River hardpoint.
This summary is AI-generated from the official solicitation.
Key Details
Official Description
--- Attachment text ---
[W912EQ26QA0500002_SOW_Bid_Schedule.pdf]
1
MEMPHIS DISTRICT STATEMENT OF WORK
GEOTECHNICAL DRILLING & TESTING SERVICES FOR HICKMAN HARDPOINT
- General. The work performed under this contract shall provide geotechnical data to support the Government’s engineering analyses and designs. Because the integrity of the subsequent engineering design is entirely dependent on the accuracy and completeness of the subsurface data, all work must be performed with the highest sta...
Change History
Critical change · Deadline
Hickman Borings Drilling and Testing
The open date moved from September 27, 2026 to October 21, 2026, a shift of 24 days later. Applicants get a later start to the application window, so the earliest submission point is pushed back by nearly four weeks. For business-development planning, teams that had scheduled proposal drafting or partner outreach around the September opening should re-baseline their timelines, since preparation time before the window opens is now longer. The later open date does not by itself change the close date or other requirements, so confirm the closing deadline in the updated solicitation before adjusting internal milestones.
Critical change · Deadline
Hickman Borings Drilling and Testing
The application close date was extended from October 12, 2026 to October 26, 2026, a shift of 14 days later. Applicants now have two more weeks to submit, so the deadline moved from the earlier date to the later one. Teams that were planning to finish by October 12 can relax that target, but the new deadline should still be treated as firm, and internal review and submission timelines should be re-planned around October 26.
Material change · Scope + Requirements + Attachment + Description
Hickman Borings Drilling and Testing
- The previous version was an amendment (SF 30) whose purpose was to add a bid schedule with base and four options, with quantities such as 300 LF sonic drilling, 50 LF rock coring, and 24 Atterberg tests in the base; the updated version replaces this with a full Statement of Work for geotechnical drilling and testing at Hickman Hardpoint.
- New requirements now defined: river-based roto-sonic borings and rock coring at designated coordinates (Figures 1 and 2) to recover intact cemented sand and gravel samples for unconfined compressive strength testing.
- Operational window is fixed at September 1 through December 31 (low-water season), with operational velocity of 4 to 7 fps at river stages of 5.0 to 15.0 feet, referenced to gage MS113.
- New monitoring duties: record river stage at start and finish of each boring, measure platform freeboard, and measure sample depths relative to the barge deck.
- Equipment requirements: a drilling system able to do both rock coring and roto-sonic work, and a stable river platform, with multi-point anchoring recommended because conventional spud barges have failed at this site.
- Data requirements: results and boring logs must be entered into the Bentley OpenGround database, and the Contractor must coordinate with USCG, USACE, and LOMRC for permits and daily shutdown hours.
Why it matters: bidders must now price for hybrid or multi-point anchoring, a narrow seasonal work window, and monitoring and database obligations that were not in the earlier schedule-only amendment.
Informational change · Description
Hickman Borings Drilling and Testing
Description information changed.
Hickman Borings Drilling and Testing
New opportunity: Hickman Borings Drilling and Testing
Similar Opportunities
Get Alerts for Opportunities Like This
RallyProp monitors 17 funding and innovation sources and sends instant alerts when opportunities match your technology and capabilities.
Build Your Free Lane