This solicitation closed on November 13, 2026
View current Department of Defense opportunities →Vandenberg SFB Tank Inspection
AI Overview
Seeks a contractor to perform an internal API 653 inspection of a floating-roof fuel storage tank at Vandenberg Space Force Base, including bottom scanning, settlement and roundness surveys, and engineering evaluation. The work supports tank integrity and continued safe fuel storage.
This summary is AI-generated from the official solicitation.
Key Details
Official Description
--- Attachment text --- [Vandenberg_RFI_Responses.pdf] Vandenberg RFI Responses 1. Based on the historical data provided, it appears that the IFR has been replaced. Can the installation confirm what type of IFR is in the tank now? Steel pan, aluminum skin pan, aluminum honeycomb pan? The floating pan is aluminum honeycomb. 2. Is there ladder access from the fixed roof to the IFR (for leg setting)? Yes 3. Wiper seal. PWS 3.2.4 requires a US-made closed-cell cast urethane double wiper seal in 28-ft ...
Change History
Critical change · Deadline + Submission + Description
Vandenberg SFB Tank Inspection
The attachment text shown in the two versions appears identical in the portion provided; both contain the same Vandenberg RFI responses, Q&A table, and BCS comments, ending at the same truncated point ("Follow what is in the PWS & Attachment B (which i..."). I cannot identify any added, removed, or reworded requirement, objective, restriction, or technical focus between the previous and updated description.
If there is a substantive difference, it lies beyond the truncated text shown, so a full comparison of the complete attachment would be needed to report specific changes.
Critical change · Scope + Requirements + Submission + Attachment + Deadline + Description
Vandenberg SFB Tank Inspection
- Tank 1702 inspection timing: The inspection is now explicitly scheduled No Earlier Than August 2027, after the FAC 1703 repair project, with fuel to be pumped into new STI tanks in place by August 2027. Period of performance is adjusted to 365 days based on award on or around January 7, 2027.
- New STI tank location: New STI tanks will sit in the same location as FAC 1703, roughly 50 yards from FAC 1702.
- Truck certification: Any truck used to transfer about 5,000 gallons of fuel must be "certified clean" before arriving onsite.
- Data sheet page limit: The wiper seal manufacturer data sheet does not count against the 5-page proposal limit.
- Inspection documentation: Wording now states the inspection proceeds on available documentation, with the earlier "and field measurements" phrasing dropped in the Q3 response.
- New Q&A items 10–12 were added covering STI tank location, distance to Tank 1702, and truck certification.
Why it matters: offerors must plan the schedule around an August 2027 start, the 365-day performance period, and certified-clean transport for fuel transfers, and can exclude the data sheet from the page count.
Material change · Requirements + Scope + Description + Submission
Vandenberg SFB Tank Inspection
- New RFI responses added (Q3–Q9): The updated description adds answers covering wiper seal data sheets and page limits, the Tank 1702 IFR manufacturer match, pre-quote site visits and waste manifests (the installation will typically sign as generator), bonds and insurance (no bonds specified; insurance type to be clarified), rim-space measurements (contractors should assume a range and verify on site), and the requirement to comply with the 28-ft continuous wiper spec and the manufacturer's riser/bolting instructions.
- Tank 1702 inspection timing and period of performance: The inspection will not occur until the FAC 1703 Repair by Replacement project is complete, with Jet A fuel pumped into new STI tanks expected by August 2027. The period of performance is adjusted to 365 days.
- Notice purpose: Amendment 0005 is described as providing the last remaining RFI responses, replacing the prior Amendment 0004 framing.
Why it matters: Offerors must now plan around a delayed Tank 1702 schedule, a 365-day performance period, and a fuel-transfer approach tied to new tank availability, and must verify rim-space dimensions on site rather than relying on fixed figures.
Material change · Deadline + Requirements + Description
Vandenberg SFB Tank Inspection
- The previous version contained RFI responses 1–3 (IFR type, ladder access, and a question on other items), while the updated version expands the RFI responses to a full table covering about ten questions.
- New RFI topics added include: whether retrospective testing of 2016 repairs (API 650 Section 8 examinations) is required (answer: no, evaluation is limited to current PWS inspections); availability of 2016 reconstruction documentation (proceed on available records and field measurements if missing); whether the interior tank bottom coating requires removal or surface preparation, with a NACE Level II or higher investigator required for bottom scanning and UT (paragraph 4.2.3); MFL screening with UT verification and at least five UT locations per bottom plate (paragraph 4.2.2).
- A separate roundness survey is confirmed as required, distinct from the API 653 Annex B settlement survey in PWS 4.2.2.1, with the contractor free to choose method and means.
- Secondary containment documentation and drain/release-valve configuration are to be provided if available, otherwise inspection proceeds on field measurements (PWS 4.2.4–4.2.4.2).
- All Appendix B 3D analysis items in the API 653 report template are confirmed as deliverables (shell distortion, bottom elevation mapping, out-of-plumbness and out-of-roundness analyses), with Attachment F treated as a template where items may be omitted if not applicable.
- Engineering evaluation scope is clarified to follow the PWS and Attachment B (API 653), with specialized analyses such as brittle-fracture assessments not mandatory unless applicable.
Why it matters: Applicants now know the 2016 repairs need no retrospective testing, that a separate roundness survey and coating/bottom-inspection work with a NACE-qualified investigator are in scope, and that the 3D analysis deliverables are required, which affects cost and staffing estimates.
Critical change · Deadline + Scope + Attachment + Description
Vandenberg SFB Tank Inspection
- The attachment changed from the full Performance Work Statement (PWS_VAN_FY27_PO_03) to a set of Request for Information (RFI) responses, so the detailed scope, Key Personnel, suitability-for-service, and equipment requirements no longer appear in this version.
- The notice description now says the purpose of Amendment 0003 is to extend the submission deadline by two weeks to 27 November 2026 and to post RFI responses issued so far.
- The RFI responses confirm the floating pan (internal floating roof) in the tank is aluminum honeycomb, not steel or aluminum skin.
- The responses confirm ladder access exists from the fixed roof to the floating roof for leg setting.
Why it matters: applicants should use the extended November 27, 2026 deadline and review the RFI answers for pan type and access, since they affect planning for leg setting and equipment. Applicants should also check the full PWS (earlier version) for requirements that the RFI answers do not restate.
Critical change · Deadline
Vandenberg SFB Tank Inspection
The close date moved later, from October 30, 2026 to November 13, 2026. That is a shift of 14 days (two weeks).
Applicants now have two more weeks to prepare and submit. Teams that had planned around the October 30 deadline should update their internal timelines, but the earlier date should no longer be treated as the cutoff for submission.
Critical change · Submission + Requirements + Scope + Attachment + Contact + Description
Vandenberg SFB Tank Inspection
This is a substantive replacement of the description, not a wording tweak. The previous attachment was an addendum to FAR 52.212-1 (submission instructions, evaluation factors, and a 5-page proposal limit). The updated attachment is the Performance Work Statement (PWS) for the same Department of Defense fuel tank inspection requirement, now at Vandenberg SFB, CA.
- Scope now defined in detail: removal and disposal of fuel, transfer of remaining fuel, tank cleaning, wiper seal replacement, and an AST internal inspection on tanks listed in Attachment B.
- Firm Fixed Price contract type specified, and work must be done during 0730-1630 weekday hours outside federal holidays.
- Key personnel required: a certified API 653 Inspector and a Project Manager.
- Fuel quantity control: the contractor must call the installation 72 hours before mobilization to confirm tank fuel quantities match the quoted amounts and may not remove or dispose of more fuel than stated.
- Equipment and materials specifications: gaskets (ASME B16.21, Buna-N), flange bolts and washers, and periphery double wiper seals with stated flexibility and compression requirements. Contractor must supply all tools and calibrated inspection equipment.
- Suitability-for-service rules: a "first, do no harm" repair approach, a minimum remaining thickness of 100 mils at next inspection, and repair decisions applied to individual indications rather than averaged across plates.
- Organizational conflict of interest and security requirements added.
Why it matters: applicants now need to price and staff to these technical and staffing requirements, not just submit the earlier administrative proposal format.
Critical change · Deadline
Vandenberg SFB Tank Inspection
The open date moved from September 30, 2026 to October 8, 2026, a shift of 8 days later. Applicants get eight more days before the solicitation opens for submissions, so the window to prepare is slightly shorter in calendar terms only if they were planning around the earlier date for early-stage work; otherwise the delay gives more preparation time before the opening. Business-development teams should update their internal timelines, including any pre-submission outreach, partner commitments, or budget planning keyed to the original September 30 opening.
Informational change · Description
Vandenberg SFB Tank Inspection
Amendment 0001 adds the missing Addendum to 52.212-1, with new submission instructions and evaluation details:
- Proposals must be one PDF of no more than five pages, sent by email to the Contract Specialist and Contracting Officer. The price worksheet, cover page, amendment acknowledgements, and required representations or certifications do not count toward the limit; the Government may not review pages beyond five.
- Quotes must include the inspector’s certification number and a one-page resume, plus three completed, comparable projects from the past five years. The examples should show experience draining fuel, disposing of unacceptable fuel, cleaning tanks, and performing API 653 inspections. Subcontracted work and the subcontractor’s relevant experience must be identified.
- Questions must be submitted in writing at least seven calendar days before the proposal due date. Prices must remain firm for 60 days after the receipt deadline.
- Experience ratings may favor stronger or multiple comparable projects; the Government may contact references. Award is on a best-value basis.
- The addendum states that funds are not presently available, so no award will be made until funding is available.
Applicants should use the new instructions to prepare and format their quotes; the notice says the amendment provides a previously missing document.
Vandenberg SFB Tank Inspection
New opportunity: Vandenberg SFB Tank Inspection
Similar Opportunities
Get Alerts for Opportunities Like This
RallyProp monitors 17 funding and innovation sources and sends instant alerts when opportunities match your technology and capabilities.
Build Your Free Lane