This solicitation closed on November 6, 2026
View current Department of Defense opportunities →106 CE ELECTRICAL LOOP REPAIR
AI Overview
This Air National Guard solicitation seeks a contractor to repair and reconfigure a 13.8 kV medium-voltage electrical loop at Francis S. Gabreski ANGB, connecting an existing line to a second transformer feed to support Building 395. It enables utility work without a base-wide power shutdown.
This summary is AI-generated from the official solicitation.
Key Details
Official Description
--- Attachment text --- [RFI_Electric_Loop__W50S8E27QA011.docx] RFI Electric Loop -W50S8E27QA011
- On Long Island, "Loop systems" as created on site, are designed to always be an open set so as to able to energize site from a second service. We do not recognize an abnormal condition currently. Please clarify.
A: Electrical Loop Circuit Configuration and Proposed Modification
The site's electrical distribution system was installed in a loop configuration, in which the primary electrical power ...
Change History
Critical change · Deadline + Scope + Attachment + Description
106 CE ELECTRICAL LOOP REPAIR
- The previous version was a full SF1449 solicitation for a 7-day, firm-fixed-price repair of the 13.8 kV medium voltage loop feeder at Building 395, with 100% performance and payment bonds required after award and funds not yet available.
- The new version replaces that with an RFI-style Q&A: the government clarifies that the site's loop was built as an open configuration with only one of two transformer feeds connected, and proposes connecting the existing line to the second feed to complete the loop.
- Scope shifts from a direct repair to a loop-completion approach tied to relocating the Building #4 underground line and connecting a future transformer, with a temporary 480V generator and weekend shutdown described as the alternative if the loop is not completed.
- A mandatory-sounding but actually optional site visit is set for 04 Nov 2026 (attendance limited to two representatives per company, names due 03 Nov).
- RFI submissions are due 05 Nov 2026 at 10:30 AM EST; the notice states the solicitation was extended because of a late RFI response.
- Why it matters: bidders should price the loop-completion work and verification of system compatibility, not just a generic repair, and should raise technical questions before the RFI deadline.
Informational change · Status
106 CE ELECTRICAL LOOP REPAIR
The solicitation status changed from open to closed. Applicants can no longer submit proposals through this opportunity, so any draft work should stop or shift toward the next open solicitation, a related follow-on announcement, or a pre-submission contact with the program office to ask whether a late or amended cycle is planned. Check the official listing for the reason (funds fully committed, cancellation, or completed review window), and if you already submitted, confirm your submission was received in the portal before the closure.
Critical change · Deadline + Scope + Requirements + Attachment + Submission + Status + Description
106 CE ELECTRICAL LOOP REPAIR
- The document changed from a project SOW (Attachment "Electrical_Loop_Repair_SOW.docx," focused on general repair scope, contractor access, badging, holidays, supervision, and scheduling) to a formal RFQ, Solicitation W50S8E27QA001 (SF 1449), for the same project WKVB179041.
- Scope is now narrowed to verifying active parts of the 13.8 kV medium voltage feeder and connecting the existing line to a second feed at the transformer serving Building 395.
- Acquisition is now a 100% small business set-aside under NAICS 238210, with Firm Fixed Price pricing, and quotes are due 06 Nov 2026 at 11:00 AM EST.
- New bonding terms: no bid bond; performance and payment bonds at 100% of contract price are required after award, due within 10 calendar days of award notice and before work starts.
- Funding is not yet available: FAR 52.232-18 applies, so no payment obligation exists until the Contracting Officer confirms funds in writing.
- Outage requests must now be submitted in writing at least 72 hours in advance.
- The period of performance is listed as 7 calendar days from NTP, with conflicting date references (2026 and 2027) in the line item, which applicants should clarify with the contracting officer.
106 CE ELECTRICAL LOOP REPAIR
New opportunity: 106 CE ELECTRICAL LOOP REPAIR
Similar Opportunities
W91237-27-Q-A017 Dumpster Services for East Lynn Lake
Due November 30, 2026
ActiveConstruct Egress JBPHH HI
Due January 19, 2027
ActiveDemolition of an existing building, Site Improvements and construction of a Modular Office Building at the US Merchant Marine Academy Campus, Kings Point, NY
Due December 7, 2026