DLA is seeking a contractor to design and install a 500 kW rooftop solar photovoltaic system on Building 56 at Defense Distribution San Joaquin, integrating it with the existing electrical substation and switchgear. The project aims to strengthen the site's electric power resiliency using commercially available solar technology.

This summary is AI-generated from the official solicitation.

Key Details

Agency
Department of Defense
Funding Amount
—
Release Date
November 10, 2026
Due Date
December 9, 2026

Official Description

--- Attachment text --- [SP330027Q0012_A0003.pdf]

  1. CONTRACT ID CODE | PAGE | OF PAGES AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT | 1 | 2
  2. AMENDMENT/MODIFICAITONAMENDMENT/MODIFICATIONNO. NO. | 3. EFFECTIVE DATE | 4. REQUISITION/PURCHASE REQ. NO. | 5. PROJECT NO. (If applicble) 0003 | November 16, 2026
  3. ISSUED BY | CODE | SP3300 | 7. ADMINISTERED BY (If other than Item 6) | CODE | PJHADM DLA Distribution | POC: Paul Holbert Acquisition Operations, J-7 | 717-770-4757 (P) Mifflin Aven...
View on official source

Change History

Description ChangedNov 16, 2026 at 4:48 PM

Critical change · Deadline + Scope + Attachment + Description

Electric Power Resiliency Building 56

The description now shows the attachment as Amendment 0003 (SF30 cover page) rather than the original Statement of Work, so the scope text itself is no longer the solar PV SOW.

  • Scope of work text removed from the description: the earlier version contained the full Building 56 SOW (750 kW AC rooftop PV, 21% efficient panels, 25-year warranties, NEMA 3R inverters, fence modifications, 110 mph wind load design, roof warranty certification, and 8 hours of training).
  • Capacity figure differs: the notice text now refers to a 500 kW AC rooftop system, while the prior SOW attachment specified 750 kW AC. Applicants should confirm the required capacity against the current SOW before pricing.
  • Amendment purpose: Amendment 0003 corrects the SF1449 cover page Block 8 date from 12/07/2026 to 12/09/2026. Amendment 0002 fixed a faulty Attachment 2 upload, and Amendment 0001 added the SOW.
  • Why it matters: the response date moves to 12/09/2026, and all other terms remain unchanged. Bidders should work from the corrected Attachment 2 and the 500 kW figure, and verify the 750 kW reference in the earlier SOW is not the operative requirement.
Description ChangedNov 13, 2026 at 4:47 PM

Material change · Scope + Attachment + Requirements + Description

Electric Power Resiliency Building 56

  • Solar capacity increased: The PV system size rose from 500 kW AC to 750 kW AC, with the peak output requirement at the utility meter now tied to the awarded capacity (500 kW minimum "or other capacity depending on final contract value").
  • Scope of work attached: The previous version only referenced a Scope of Work being added; the updated version contains the full Attachment 2 requirements, including 21% minimum-efficiency panels with 25-year warranties, 5 spare panels, SMA inverters with 10-year warranties and 2 spares, and an HMI display panel.
  • Detailed technical requirements: New specifics include 110 mph wind-load design per ASCE 7-16 and UFC 3-440-01, roof-warranty certification from Duro-Last, substation fence modification and grounding, undervoltage-tripping breaker logic, NEC/NFPA 110E labeling, and 8 hours of operator training.
  • Design approval gate: The contractor must submit a PE-certified final design for government approval at least four weeks before construction, with calculations proving the rated output.

Why it matters: Applicants must now price a larger 750 kW system and meet a much more detailed technical and warranty specification, which will raise cost and design effort.

Description ChangedNov 12, 2026 at 8:47 PM

Material change · Description + Requirements + Submission + Contact + Attachment

Electric Power Resiliency Building 56

  • The previous description was the full RFQ attachment text (SF 1449 with the solar PV scope of work for Building 56, including the 500 kW AC system requirements, panel and inverter specs, and fencing/grounding requirements).
  • The updated description is Amendment 0001 (SF 30), which states it is issued to add Attachment 2, the Scope of Work, and that all other terms remain unchanged.
  • The amendment notice text now carries the same 500 kW solar PV scope language, but labels the document "Statement of Work" instead of "Scope of Work" in the notice body.
  • Practically, the substantive technical requirements (500 kW AC roof-mounted PV, 21% efficient panels with 25-year warranty, inverter and HMI requirements, substation fencing and grounding) are largely unchanged in wording; the key change is the procedural addition of the separate Attachment 2 Scope of Work.
  • Why it matters: applicants should review Attachment 2 directly for the detailed scope, since it is now formally part of the RFQ, and confirm that offers account for the amended document. The offer due date and other terms were not changed by this amendment.
Opportunity AddedNov 10, 2026 at 7:50 PM

Electric Power Resiliency Building 56

New opportunity: Electric Power Resiliency Building 56

Similar Opportunities

Get Alerts for Opportunities Like This

RallyProp monitors 17 funding and innovation sources and sends instant alerts when opportunities match your technology and capabilities.

Build Your Free Lane