Official Description
--- Attachment text --- [Amendment_0002_26RA033_Arcadia_Wet_Well_Extend_Due_Date_21_Oct_2026.pdf] 11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and re...
Change History
Critical change · Deadline
Arcadia Wet Well Rehabilitation
The open date moved from September 24, 2026 to October 21, 2026, a delay of 27 days. Applicants get the opportunity to begin submitting later than previously planned, but the change does not by itself shorten the response window if the close date stayed the same. Businesses should re-check their proposal timelines, since any internal drafting, teaming, or registration work scheduled around the earlier opening should be pushed back accordingly. Because the close date was not reported as changed, the effective preparation period is now roughly four weeks shorter, which matters for teams that need lead time for capability statements or partner agreements.
Critical change · Deadline
Arcadia Wet Well Rehabilitation
The close date moved later, from October 26, 2026 to November 9, 2026. That is a shift of 14 days (two weeks), so applicants gain two additional weeks to submit.
Why it matters for applicants:
- More time to finalize proposals, budgets, and required certifications.
- Teams planning around the original October deadline should re-sequence internal reviews, partner commitments, and any upcoming submission milestones.
- Questions submitted to the contracting or program office should be checked against the new timeline, since response windows may also have shifted.
Critical change · Deadline + Attachment + Description
Arcadia Wet Well Rehabilitation
- The response due date moved from 19 October 2026 (Amendment 0001) to 26 October 2026 in the prior version, and this amendment extends it again to 9 November 2026 at 2:00 PM CDT (the 26 October 2:00 PM CDT deadline is replaced).
- The pre-bid site visit on 14 October 2026 at 11:00 AM CDT at 9000 E 2nd Street, Arcadia, OK, from Amendment 0001, is no longer the only scheduling change; the new amendment itself makes no other scope changes.
- All other terms and conditions remain unchanged.
Why it matters: applicants gain roughly two extra weeks to prepare and submit proposals, so teams should update internal timelines and calendar the new 9 November 2026, 2:00 PM CDT deadline, while still acknowledging amendments as required to avoid rejection.
Informational change · Description
Arcadia Wet Well Rehabilitation
- A pre-bid site visit was added for October 14, 2026, at 11:00 a.m. CDT. Attendees should meet at the access-road entry gate at 9000 E 2nd Street, Arcadia, OK 73007.
- The response due date moved from October 19 to October 26, 2026, giving applicants an additional week to submit. All other terms and conditions remain unchanged.
Arcadia Wet Well Rehabilitation
New opportunity: Arcadia Wet Well Rehabilitation
Similar Opportunities
Get Alerts for Opportunities Like This
RallyProp monitors thousands of funding sources and sends instant alerts when opportunities match your technology and capabilities.
Build Your Free Lane