LOWER BRULE NORTH SHORELINE STABILIZATION AND ECOSYSTEM RESTORATION, ELEMENT 2
AI Overview
This Army Corps of Engineers amendment revises pricing and payment procedures for a Missouri River shoreline stabilization and ecosystem restoration project. It clarifies bid items for breakwater structures, riprap placement, excavation, topsoil, culverts, and related earthwork.
This summary is AI-generated from the official solicitation.
Key Details
Official Description
--- Attachment text --- [Amd_0001_for_W9128F27BA007_Lower_Brule_Elment_2.pdf]
- CONTRACT ID CODE | PAGE OF PAGES AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT | J | 1 | 3
- AMENDMENT/MODIFICATION NUMBER | 3. EFFECTIVE DATE | 4. REQUISITION/PURCHASE REQUISITION NUMBER | 5. PROJECT NUMBER (If applicable) 0001 | 12 NOV 2026 | 517089
- ISSUED BY | CODE | W9128F | 7. ADMINISTERED BY (If other than Item 6) | CODE
W071 ENDIST OMAHA KO CONTRACTING OFFICE, 1616 CAPITOL AVENUE OMAHA, NE 68102-4...
Change History
Critical change · Submission + Requirements + Attachment + Deadline + Description
LOWER BRULE NORTH SHORELINE STABILIZATION AND ECOSYSTEM RESTORATION, ELEMENT 2
- The amendment (Amendment 0001, dated 10 Nov 2026 / effective 12 Nov 2026) replaces Specification Section 01 20 00, "Pricing and Payment Procedures," with a revised version marked "Am-0001."
- The revised section restructures the payment provisions tied to each bid item: island breakwater placement (0002), mobilization/demobilization (0001), riprap (0003), spalls and underwater fill (0006), excavation cut (0004), excavation fill (0005/0006), loamy topsoil (0007/0008), aggregate surface and base course (0009), culvert placement (0010), and all remaining work (0011).
- Each item now has explicit subsections for work included, measurement, and payment, and riprap and spalls add scale-method and scale requirements for tonnage measurement.
- The earlier bid schedule and solicitation text otherwise remain in effect; the amendment states all other terms are unchanged.
- Why it matters: bidders must price against the revised measurement and payment rules, so unit prices for riprap, spalls, and excavation should be checked against the new scale-based measurement method before submitting. The bid opening remains 3 Dec 2026 at 2:00 p.m.
LOWER BRULE NORTH SHORELINE STABILIZATION AND ECOSYSTEM RESTORATION, ELEMENT 2
New opportunity: LOWER BRULE NORTH SHORELINE STABILIZATION AND ECOSYSTEM RESTORATION, ELEMENT 2
Similar Opportunities
USACE SPK DBB Construction - LAR C3B North - Sacramento, CA
Due December 16, 2026
ActiveMISSISSIPPI RIVER BASIN BETTENDORF, IOWA LOCAL FLOOD PROTECTION BETTENDORF, IOWA 2024 EVENT PL84-99 FLOOD REPAIRS
Due December 17, 2026
ActiveTwo Munition Igloos at Ellsworth AFB, South Dakota
Due December 8, 2026
Get Alerts for Opportunities Like This
RallyProp monitors 17 funding and innovation sources and sends instant alerts when opportunities match your technology and capabilities.
Build Your Free Lane